AQW 2280/17-22 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure, in relation to the current proposed timescale for the construction of five grade-separated junctions, whether there is any opportunity to speed up the insertion of a median barrier for safety reasons on the entirety of the A1 between Hillsborough and Loughbrickland.
Asked by Paula Bradshaw MLA on 18 February 2020
- Answered
- Written
- Tabled
- 18 February 2020
- Answer due by
- 4 March 2020
- Answered
- 3 March 202014 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
Improving connectivity between Belfast and Dublin is a key priority for me, as is promoting road safety. The proposed A1 Junctions Phase 2 road improvement scheme includes the construction of four grade separated junctions, a new on-slip at Castlewellan Road, Banbridge and a new link road at Milebush Road, Dromore.
In advance of the main scheme, approximately 6.5km of central reserve safety barrier has been installed along the A1 over the past few years. However, the main scheme represents the best way forward in terms of further safety measures.
In the meantime, I can assure the Member that my officials are continuing to explore opportunities and timescales for other safety measures on this route.