AQW 2850/16-21 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure to outline the reasons for the delay, in relation to the initially published proposals, in implementing the new Belfast Rapid Transit system from Belfast city centre to Finaghy Road North.

Asked by Paula Bradshaw MLA on 12 September 2016

  • Answered
  • Written
Tabled
12 September 2016
Answer due by
27 September 2016
Answered
21 September 20169 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

In 2015 the operational date for the Belfast Rapid Transit (BRT) system was revised from 2017 to September 2018. The implementation of the BRT system is not only dependent on the completion of the BRT road infrastructure and procurement of vehicles, but also on the delivery of a number of significant interdependent projects. These include:

Translink’s Ticketing Replacement project – which is required to be in place to provide off-board ticketing for BRT; and

Translink’s Duncrue Depot project – which will house and maintain approximately 100 buses, including the new fleet of BRT vehicles.

In 2015, due to budgetary uncertainty, it became clear that it would not be possible to deliver all the elements to enable BRT to become operational in 2017. It was therefore decided to revise the operational date to September 2018. This revised operational date was assessed as achievable by an independent external Project Assessment Review.

Implementation of the first phase of BRT, which will connect East Belfast, West Belfast and Titanic Quarter via the city centre, is progressing well and is on schedule for the commencement of services in September 2018.