AQO 3077/22-27 Oral question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an update on the current status of Belfast Rapid Transit Phase 2, including anticipated timelines for completion.

Asked by Paula Bradshaw MLA on 29 January 2026

  • Answered
  • Oral
  • After due date
Tabled
29 January 2026
Answer due by
9 February 2026
Answered
10 February 202612 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

On the 25th February 2025 I was pleased to announce the next steps for the Belfast Rapid Transit 2 project which will see implementation of this innovative service across the North and South of the city, bringing the benefits already established by the Glider service to communities living along this route.

The Outline Business Case for the project was submitted to DoF on 25th November 2025 with an estimated delivery cost of £124.5m and this was approved on 22nd December 2025.

Funding of £35m has been allocated from our Belfast Region City Deal partners, and I have committed an additional £13 million from my Department which will enable the commencement of a phased delivery.

While a significant shortfall funding remains, I am committed to working with my colleagues in the executive and our Belfast Region City Deal partners to identify opportunities to address this.

Following approval of the Outline Business Case, my officials are now in the process of appointing engineering consultants to progress the detailed design phase.

A detailed delivery programme will be developed following the appointment of consultants however it is currently expected that, subject to securing the additional funding required, the BRT2 project could be completed by 2033.