AQW 10784/22-27 Written question to the Minister of Education

To ask the Minister of Education what steps he is taking to ensure work is progressed urgently on the roof replacement at Cairnshill Primary School.

Asked by Paula Bradshaw MLA on 24 April 2024

  • Answered
  • Written
Tabled
24 April 2024
Answer due by
10 May 2024
Answered
8 May 202414 days after tabling
Department
Department of Education
Priority question
No

Answer

An architect led design team has been appointed for the roof replacement works at Cairnshill Primary School. It is currently anticipated that design will be completed mid-May, with construction to commence in June.