AQW 3534/22-27 Written question to the Minister of Education
To ask the Minister of Education for an update on the planning and procurement for Hunterhouse College within the Capital Works Programme.
Asked by Paula Bradshaw MLA on 26 September 2022
- Answered
- Written
- After due date
- Tabled
- 26 September 2022
- Answer due by
- 11 October 2022
- Answered
- 12 October 202216 days after tabling
- Department
- Department of Education
- Priority question
- No
Answer
The Education Authority is in the process of procuring Integrated Consultancy Teams (ICTs) for the major capital works that I announced on 21 March 2022. It is anticipated that the ICT contracts will be awarded in spring 2023.
Following appointment, the ICTs will undertake technical feasibility studies, which will inform the business cases.