AQW 774/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an update on the provision of a pedestrian and cycle bridge from the Gasworks to Ormeau Embankment, Belfast.

Asked by Paula Bradshaw MLA on 30 May 2022

  • Answered
  • Written
Tabled
30 May 2022
Answer due by
16 June 2022
Answered
8 June 20229 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

The statutory processes for this project have been completed and, following its inclusion in the Belfast Region City Deal, my officials have commenced preparations for the procurement phase. It is estimated that it will take approximately 3.5 years to complete the procurement, detailed design and construction phases.