AQW 401/17-22 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure to outline the timescale for release of funding to deliver the Carryduff Greenway.

Asked by Paula Bradshaw MLA on 16 January 2020

  • Answered
  • Written
  • After due date
Tabled
16 January 2020
Answer due by
31 January 2020
Answered
3 February 202018 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

The Carryduff Greenway scheme is a Lisburn and Castlereagh City Council project. My Department provided a small amount of funding to assist in the development of a feasibility study and a detailed design.

I have inherited severe and challenging budget constraints and therefore have to look carefully at solutions to help support the delivery of projects to meet my priorities of connecting our communities and enhancing our environment. Over the coming weeks I want to carefully consider how the provision of greenways and other cycling infrastructure can assist as part of my vision to greater sustainable transport options that connect communities and improve lives.